FirstEnergy Corp. announced an update to its long-term 2026-2030 strategic plan on November 20, 2026, following regulatory approval for a new generation facility in West Virginia. The company stated that it is raising its long-term Core Earnings per share compound annual growth rate outlook for the 2026-2030 period to 7% to 9%, targeting the upper half of the range.

The update includes an increase to the company’s 2026-2030 capital investment plan, known as Energize365. The total capital investment for the period is now projected to be $38 billion, up from the previously announced $36 billion. This increase is attributed to the order issued by the Public Service Commission of West Virginia on November 17, 2026, which granted Monongahela Power Company and The Potomac Edison Company a Certificate of Public Convenience and Necessity to construct the Maidsville Energy Center.

FirstEnergy plans to fund approximately 35% of the capital investment associated with the Maidsville Energy Center project with equity and/or equity-like securities. As a result, the company’s total anticipated equity financing needs for the 2026-2030 period are increasing from $2.0 billion to $2.8 billion. The regulatory order also approved a new generation surcharge to provide for cash recovery of financing costs while the Maidsville Energy Center project is under construction.

In addition to the generation investment, FirstEnergy expects to increase its transmission investments by at least 25% compared to its current $19 billion plan. The company also issued an initial request for proposals for an additional 3 gigawatts of combined-cycle natural gas generation and is exploring near-term bridge power options.